Project Status
2/19/2018
- Layout table design is complete.
- Tooling and house projects are delaying the start.
1/19/2018
- Still have outstanding quotes, will be calling again to see if I get better results. I'm giving them the benefit of the doubt that the holidays were just a crazy time and my correspondence was lost in the nether.
- I'm nearing completion on my layout table design. Once completed I will determine materials needed and begin work.
1/3/2018
- A lot has been accomplished so that I can begin on the frames soon. I have most of my social media up and running and I also have the GoFundMe site working and can begin accepting donations. I'm still gathering quotes for lumber and plywood. I'm beginning the process of creating my Layout Table.
12/2/2017
- I've created this page to document things as I begin my build. All the other pages are the plans. This is where my plans meet reality. I hope to begin my first cuts shortly after the start of 2018.